Norfolk’s Terminal Boulevard resurfacing is complete

Southsidedaily.com is your source for free local news and information in Virginia Beach

Terminal Boulevard's resurfacing is complete. (Photo courtesy of VDOT)

Terminal Boulevard’s resurfacing is complete. (Photo courtesy of VDOT)

Terminal Boulevard’s $5 million resurfacing project finished Nov. 18, nearly two months ahead of the original contract date.

Now, the 2-mile stretch between Hampton Boulevard and  I-564 has a 6-inch layer of asphalt. The I-64 off-ramp to Terminal Boulevard west was resurfaced, too. Other improvements include new curbs, guard rails, gutters and storm water pipes, according to a Virginia Department of Transportation news release.

The project repaired a major road connecting to the Port of Virginia’s Norfolk International Terminals and Naval Support Activity Hampton Roads.

 